Exact site not public
Map
2 Cedar Wind in Texas: the ring is the region's center, not the site. Outline: Natural Earth and US Census Bureau, both public domain.
2 Cedar Wind
Wind
- Capacity
- Capacity: sourceERCOT · Open licenseMW
- Queue position
- 28INR0286
- In-service date
- (stated)
- Location
- Fannin County, Texas (exact site not stated)EstimateEstimated from the county centroid. The source names the county, not the site. Source: ERCOT. How we estimate →
Details
Who’s behind it
- Developer
- SunWR, LLC
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Wind source: “Wind - Wind Turbine”
- Connects at
- Tap 345kV 1729 Valley South – Anna Switch 2373Connection point795.4 MW active (3 of 3 projects).
At this site
2 records at Whitewright Solar 2At this siteGrouped by the same grid connection point and developer. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | Whitewright Solar 2 | Solar | 301.7 | Studied |
| Co-located, other technology high confidence | 2 Cedar Wind this record | Wind | 180 | Studied |
Also at this interconnection point (1)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- White Bright BESS Storage, 313.7 MW, studied at Tap 345kV 1729 Valley South – Anna Switch 2373
Sources ERCOT
Timeline
- Stated In-service date stated by ERCOT.
- Observed as studied in ERCOT (source status: “Active”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources ERCOT