Amerada
Solar + storage
- Capacity
- Capacity: sourceERCOT · Open licenseMW
- Queue position
- 26INR0082, 26INR0084
- In-service date
- (stated)
- Location
- Freestone County, Texas
Details
Who’s behind it
- Developer
- Cypress Creek Renewables
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Solar + storage source: “Solar - Photovoltaic Solar + Other - Battery Energy Storage”
- Capacity (MW)
- 452.4 Capacity is the interconnection request in ERCOT GIS Report (Generator Interconnection Status). The 1 generator listed in EIA-860M Preliminary Monthly Electric Generator Inventory (listed under Sources) total 300 MW nameplate.
- Connects at
- Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5Connection point452.4 MW active (1 of 1 projects).
- EIA plant
- 67649 generator AMERA
Timeline
- Stated In-service date stated by ERCOT.
- Observed as studied in ERCOT (source status: “Active”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.
Sources
2 sourcesAround this project
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Timber Cove Solar Studied | Solar | 2.3 mi | 100.5 |
| Big Brown Postponed | Coal | 4.5 mi | 800 |
| Armadillo Solar Center Under construction | Solar | 10.9 mi | 150.5 |
| Apex Bethel Energy Center Postponed | Storage | 11.9 mi | 317 |