Black Hills Playa B Solar
Solar + storage
As filed: BLACK HILLS PLAYA B SOLAR
- Capacity
- Capacity: sourceCAISO · Open license, with creditMW
- Queue position
- 1652
- In-service date
- (stated)
- Location
- CLARK County, Nevada (exact site not public)
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Connects at
- Sloan Canyon Switching Station 230kVConnection point126.6 MW active (1 of 4 projects).
At this site
2 records at BLACK HILLS PLAYA A SOLARAt this siteGrouped by the same grid connection point and project name. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | BLACK HILLS PLAYA A SOLAR | Solar + storage | 100 | Withdrawn |
| Earlier filing, superseded low confidence | BLACK HILLS PLAYA B SOLAR this record | Solar + storage | 100 | Withdrawn |
Also at this interconnection point (2)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- Roccasecca BESS LLC Storage, 126.6 MW, under construction at Sloan Canyon Switching Station 230kV
- SLOAN ENERGY CENTER Solar + storage, 448 MW, withdrawn at Sloan Canyon Switching Station 230kV
Timeline
- Observed as withdrawn in CAISO.
- Stated In-service date stated by CAISO.
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources CAISO