Exact site not public
Map
Caesar Storage in Texas: the ring is the region's center, not the site. Outline: Natural Earth and US Census Bureau, both public domain.
Caesar Storage
Solar + storage
- Capacity
- Capacity: sourceERCOT · Open licenseMW
- Queue position
- 29INR0132, 29INR0131
- In-service date
- (stated)
- Location
- Borden County, Texas (exact site not stated)EstimateEstimated from the county centroid. The source names the county, not the site. Source: ERCOT. How we estimate →
Sources
-
View at source →
ERCOT · 2 records (29INR0132, 29INR0131)
ERCOT GIS Report (Generator Interconnection Status)
ERCOT Website User Agreement clause 5, retrieved 2026-09-12 — "raw data provided in public portions of this website may be used, reproduced, and redistributed in compilations, charts, and analyses without maintaining such notices"
Units and requests (2)
How these combine
This project is one site. Each row is one unit or request a register lists for it: a generator in EIA-860M, a stage in NESO’s register, a request in a grid queue. Capacity is the live interconnection requests’ MW added up where there are any, plus any listed generator of a technology no request covers; otherwise the generators’ MW added up. The status is the most advanced any row reports; a withdrawn row ends the project only when no other row carries it on.
| Source | Record | Name | Technology | MW | Status | Proposed COD |
|---|---|---|---|---|---|---|
| ERCOT Request | 29INR0132 | Caesar Storage | Storage | 205.5 | Contracted “Completed” | Nov 26, 2029 |
| ERCOT Request | 29INR0131 | Caesar Solar | Solar | 181.6 | Contracted “Completed” | Nov 26, 2029 |