Show on map
Exact site not public
Map
Clutch City Solar Phase II in Texas: the ring is the region's center, not the site. Outline: Natural Earth and US Census Bureau, both public domain.
Clutch City Solar Phase II
Solar
No longer listedNo longer listedNo longer listed in any register since .
- Capacity
- Capacity: sourceERCOT · Open licenseMW
- Queue position
- 25INR0330
- In-service date
- (stated)
- Location
- Brazoria County, Texas (exact site not stated)EstimateEstimated from the county centroid. The source names the county, not the site. Source: ERCOT. How we estimate →
Details
Who’s behind it
- Developer
- HZ Solar I, LLC
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Solar source: “Solar - Photovoltaic Solar”
- Connects at
- tap 138kV 42960 Mustang Bayou – 42100 Hudson CKT #04Connection point452 MW active (2 of 2 projects).
At this site
2 records at Clutch City Solar Phase IIAt this siteGrouped by the same grid connection point and developer. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | Clutch City Solar Phase II this record | Solar | 251.3 | Contracted |
| Another phase high confidence | Clutch City Solar Phase I | Solar | 200.8 | Contracted |
Sources ERCOT
Timeline
- Stated In-service date stated by ERCOT.
- No longer in ERCOT's report (reason not stated).
- Observed as contracted in ERCOT (source status: “Completed”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources ERCOT