Exact site not public
Map
Didcot B in United Kingdom: the ring is the region's center, not the site. Outline: Natural Earth and US Census Bureau, both public domain.
Didcot B
Gas, combined cycle
- Capacity
- Capacity: sourceNESO · Open license, with creditMW
- Queue position
- PRO-000122
- In-service date
- (stated)
- Location
- Didcot 400kV Substation, United Kingdom (exact site not stated)EstimateEstimated from a named place. The source names a nearby place, not the site. Source: NESO. How we estimate →
Details
Who’s behind it
- Developer
- RWE Generation UK Plc · part of RWE AktiengesellschaftOwnership claimOwnership link recorded from the companies' own published statements; no date stated by the source.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Gas, combined cycle source: “CCGT (Combined Cycle Gas Turbine);Energy Storage System”
- Connects at
- Didcot 400kV SubstationConnection point700 MW active (3 of 5 projects).
At this site
2 records at Didcot BAt this siteGrouped by the same grid connection point and developer. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | Didcot B this record | Gas, combined cycle | 1,705 | Built |
| Operating plant being expanded high confidence | Didcot A GTs | Gas, combustion turbine | 100 | Built |
Also at this interconnection point (3)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- Didcot Energy Park Storage, 300 MW, studied at Didcot 400kV Substation
- Didcot Road Storage, 300 MW, permitted at Didcot 400kV Substation
- Didcot Battery Storage, 100 MW, filed at Didcot 400kV Substation
Sources NESO
Supported by National Energy SO Open Data
Timeline
- Stated In-service date stated by NESO.
- Observed as built in NESO (source status: “Built”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources NESO
Supported by National Energy SO Open Data