Easley Solar
Solar + storage
Key facts
Solar + storage Under construction (source status: (TS) Construction complete, but not yet in commercial operation) (what this status means)- Capacity
- Capacity: sourceCAISO · Open license, with creditMW
- Queue position
- 2042
- In-service date
- (stated)
- Location
- Riverside County, California
Details
Who’s behind it
- Developer
- IP Easley, LLC
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Capacity (MW)
- 650 Capacity is the interconnection request in CAISO Public Queue Report. The 2 generators listed in EIA-860M Preliminary Monthly Electric Generator Inventory (listed under Sources) total 590 MW nameplate.
- Connects at
- Red Bluff Substation 500kVConnection point1,050 MW active (2 of 7 projects).
- EIA plant
- 68758 2 generatorsEIA generatorsPlant 68758 IPEA1, IPEA3
Timeline
- Observed as under construction in EIA-860M (source status: “(TS) Construction complete, but not yet in commercial operation”).
- EIA-860M Preliminary Monthly Electric Generator Inventory: Proposed cod 2026-09-01 → 2026-10-01.
- Stated In-service date stated by EIA-860M.
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.
Sources
2 sourcesSources
- CAISO Public Queue ReportSource: California ISO
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this project
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| SE Athos II, LLC Under construction | Storage | 4.2 km | 402.3 |
| SE Athos II, LLC Postponed | Solar | 4.2 km | 200 |
| Lycan Solar Project Contracted | Solar + storage | 24.1 km | 400 |
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- CAISO Public Queue ReportSource: California ISO