Gatsby Energy Storage Project
Storage
Key facts
Storage Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) (what this status means)- Capacity
- Capacity: sourceERCOT · Open licenseMW
- Queue position
- 27INR0139
- In-service date
- (stated)
- Location
- Pecos County, Texas
Details
Who’s behind it
- Developer
- Gatsby Energy Storage LLC
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Storage source: “Other - Battery Energy Storage”
- Capacity (MW)
- 103.4 Capacity is the interconnection request in ERCOT GIS Report (Generator Interconnection Status). The 1 generator listed in EIA-860M Preliminary Monthly Electric Generator Inventory (listed under Sources) total 103.4 MW nameplate.
- Connects at
- Fort Lancaster 138 kV Substation (PSSE Bus #76579)Connection point103.4 MW active (1 of 1 projects).
- EIA plant
- 68428 generator GTSBY
Timeline
- Stated In-service date stated by EIA-860M.
- Observed as under construction in EIA-860M (source status: “(U) Under construction, less than or equal to 50 percent complete”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.