Green River Energy Center - Hybrid
Solar + storage
Key facts
Solar + storage Built (source status: Operating (EIA-860M operating generator inventory)) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Interconnection queue
- PacifiCorp
- In-service date
- (stated)
- Location
- Emery County, Utah (exact site not stated)EstimateEstimated from the county centroid. The source names the county, not the site. Source: LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions). How we estimate →
Sources
-
View at source →
EIA-860M ·
EIA-860M Preliminary Monthly Electric Generator Inventory
US federal work — public domain
-
View at source →
Berkeley Lab ·
LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker. · license
Publication page https://eta-publications.lbl.gov/publications/queued-2026-edition-characteristics, retrieved 2026-10-23 (HTTP 200) — "Copyright Notice: The Queued Up data file is licensed CC BY 4.0. You may use, share, or adapt the dataset as long as you attribute it to Lawrence Berkeley National Laboratory and GridTracker." and "Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker. CC BY 4.0. All rights reserved." The file's Introduction sheet adds the DOE contract notice ("This dataset has been authored by an author at Lawrence Berkeley National Laboratory under Contract No. DE-AC02-05CH11231 with the U.S. Department of Energy ...") and the standard no-warranty disclaimer
Units and requests (2)
How these combine
This project is one site. Each row is one unit or request a register lists for it: a generator in EIA-860M, a stage in NESO’s register, a request in a grid queue. Capacity is the live interconnection requests’ MW added up where there are any, plus any listed generator of a technology no request covers; otherwise the generators’ MW added up. The status is the most advanced any row reports; a withdrawn row ends the project only when no other row carries it on.
| Source | Record | Name | Technology | MW | Status | Proposed COD |
|---|---|---|---|---|---|---|
| LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions) Request | PacifiCorp/787 | Green River Solar I, LLC | Solar + storage | 400 | Contracted “active” | Nov 15, 2024 |
| EIA-860M Generator | plant:67501 | Green River Energy Center - Hybrid | Storage | 800 | Built “Operating (EIA-860M operating generator inventory)” | — |