Show on map
- Combustion
- Under construction
- 10 · 100 · 1,000 MW
Map
- Combustion
- Under construction
GreenGen power station Phase II Unit 1: the source's site coordinate and 4 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
GreenGen power station Phase II Unit 1
Coal
- Capacity
- Capacity: sourceGlobal Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses) · Open license, with creditMW
- Location
- Tianjin, China
Details
Who’s behind it
- Developer
- Huaneng Tianjin Igcc Co Ltd
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Coal source: “coal / IGCC”
At this site
2 records at GreenGen power station Phase II Unit 1At this siteGrouped by the same exact location and developer. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | GreenGen power station Phase II Unit 1 this record | Coal | 400 | Canceled |
| Another phase high confidence | GreenGen power station Phase II Unit 2 | Coal | 400 | Canceled |
Sources GEM
Sources
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
Timeline
- Observed as canceled in GEM (source status: “cancelled”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources GEM
Sources
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
Around this project
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| GreenGen power station Phase II Unit 2 Canceled | Coal | 0.0 km | 400 |
| Junliangcheng power station Phase VI Unit 12 Canceled | Coal | 15.1 km | 350 |
| Tianjin Dagang power station Replacement unit 1 Under construction | Coal | 20.5 km | 660 |
| Tianjin Dagang power station Replacement unit 2 Under construction | Coal | 20.5 km | 660 |
Sources GEM
Sources
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.