Harquahala Sunrise 2
Solar + storage
As filed: HARQUAHALA SUNRISE 2
- Capacity
- Capacity: sourceCAISO · Open license, with creditMW
- Queue position
- 2029
- In-service date
- (stated)
- Location
- MARICOPA County, Arizona (exact site not public)
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Connects at
- Delaney Substation 500 kVConnection point850 MW active (3 of 7 projects).
At this site
2 records at HARQUAHALA SUNRISEAt this siteGrouped by the same grid connection point and project name. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | HARQUAHALA SUNRISE | Solar + storage | 300 | Studied |
| Another phase medium confidence | HARQUAHALA SUNRISE 2 this record | Solar + storage | 150 | Studied |
Also at this interconnection point (5)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- HARQUAHALA FLATS 2 Solar + storage, 400 MW, studied at Delaney Substation 500 kV
- ARIZONA A1 Solar + storage, 2,000 MW, withdrawn at Delaney Substation 500 kV
- PITCHFORK ENERGY Solar + storage, 500 MW, withdrawn at Delaney Substation 500 kV
- PRIMROSE HYBRID Solar + storage, 450 MW, withdrawn at Delaney Substation 500 kV
- PAPAGO Solar + storage, 300 MW, withdrawn at Delaney Substation 500 kV
Sources CAISO
Timeline
- Observed as studied in CAISO.
- Stated In-service date stated by CAISO.
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources CAISO