Loch na Cathrach Pumped Storage Hydro: the source's site coordinate and 7 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Loch na Cathrach Pumped Storage Hydro
Pumped hydro storage
- Capacity
- Capacity: sourceNESO · Open license, with creditMW
- Queue position
- PRO-000570-1, PRO-000570-2
- In-service date
- (stated)
- Location
- Scotland, United Kingdom
Details
Who’s behind it
- Developer
- Statkraft Highlands PSH Limited · part of Statkraft ASOwnership claimOwnership link recorded from the companies' own published statements; no date stated by the source.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Storage
- Technology
- Pumped hydro storage source: “Pump Storage”
- Capacity (MW)
- 550 Capacity is the interconnection request in NESO Transmission Entry Capacity (TEC) Register. The 1 generator listed in Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses) (listed under Sources) total 450 MW nameplate.
- Connects at
- Loch na Cathrach 275kV Switching StationConnection point550 MW active (1 of 1 projects).
Timeline
- Stated In-service date stated by NESO.
- Observed as permitted in NESO (source status: “Consents Approved”).
- NESO Transmission Entry Capacity (TEC) Register: Proposed cod 2029-04-30 → 2030-06-28.
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.
Sources
2 sourcesSupported by National Energy SO Open Data
Sources
- NESOSupported by National Energy SO Open Data
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
Around this project
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Carr Ban wind farm -- Canceled | Wind | 6.5 km | 23.8 |
| Druim Ba wind farm -- Canceled | Wind | 10.0 km | 30 |
| Loch Liath Wind Farm Studied | Wind | 11.0 km | 99 |
| Daviot Windfarm BEGA Filed | Wind + storage | 13.2 km | 45 |
| Farr Wind Farm - Tomatin Built | Wind | 17.9 km | 92 |
| Clune Wind Farm Filed | Wind + storage | 19.0 km | 187.2 |
| Bhlaraidh Wind Farm Built | Wind | 24.5 km | 108 |
Supported by National Energy SO Open Data
Sources
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- NESOSupported by National Energy SO Open Data