Exact site not public
Map
Merlin 2 Offshore Windfarm in United Kingdom: the ring is the region's center, not the site. Outline: Natural Earth and US Census Bureau, both public domain.
Merlin 2 Offshore Windfarm
Offshore wind
- Capacity
- Capacity: sourceNESO · Open license, with creditMW
- Queue position
- PRO-001997
- In-service date
- (stated)
- Location
- Alverdiscott 400kV Substation, United Kingdom (exact site not stated)EstimateEstimated from the connection substation. The source names the connection substation, not the site. Source: NESO. How we estimate →
Details
Who’s behind it
- Developer
- Offshore Wind Limited
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Offshore wind source: “Wind Offshore”
- Connects at
- Alverdiscott 400kV SubstationConnection point10,308 MW active (13 of 13 projects).
At this site
2 records at Merlin 2 Offshore WindfarmAt this siteGrouped by the same grid connection point and developer. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | Merlin 2 Offshore Windfarm this record | Offshore wind | 1,500 | Filed |
| Another phase medium confidence | Merlin Offshore Wind Farm | Offshore wind | 300 | Filed |
Also at this interconnection point (11)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- SSE Celtic Sea 1 Offshore wind, 1,500 MW, filed at Alverdiscott 400kV Substation
- Cormoran Offshore Wind Farm Offshore wind, 1,008 MW, filed at Alverdiscott 400kV Substation
- Alverdiscott Farm Solar + storage, 1,000 MW, filed at Alverdiscott 400kV Substation
- Celtic 2 Offshore Wind Farm Offshore wind, 1,000 MW, filed at Alverdiscott 400kV Substation
- Equinor Celtic Sea 1 Offshore wind, 1,000 MW, filed at Alverdiscott 400kV Substation
- Gwynt Glas Offshore Wind Farm 2 Offshore wind, 1,000 MW, filed at Alverdiscott 400kV Substation
- Petroc Extension Offshore Wind Farm Offshore wind, 1,000 MW, filed at Alverdiscott 400kV Substation
- Gwynt Glas Offshore Wind Farm Offshore wind, 300 MW, filed at Alverdiscott 400kV Substation
- Morwind 300 Offshore wind, 300 MW, filed at Alverdiscott 400kV Substation
- Petroc Offshore Wind Farm Offshore wind, 300 MW, filed at Alverdiscott 400kV Substation
- Alverdiscott Storage, 100 MW, filed at Alverdiscott 400kV Substation
Sources NESO
Supported by National Energy SO Open Data
Timeline
- Stated In-service date stated by NESO.
- Observed as filed in NESO (source status: “Scoping”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources NESO
Supported by National Energy SO Open Data