Show on map
- Combustion
- Wind & solar
- In development
- Under construction
- 10 · 100 · 1,000 MW
Map
- Combustion
- Wind & solar
- In development
- Under construction
Rawhide: the source's site coordinate and 1 exact-grade project within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Rawhide
Gas, combustion turbine
Key facts
Gas, combustion turbine Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Interconnection queue
- Public Service Company of Colorado (PSCO)
- In-service date
- (stated)
- Location
- Larimer County, Colorado
Details
Who’s behind it
- Developer
- Platte River Power Authority
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
- Capacity (MW)
- 223 Capacity is the sum of the 5 generators listed under Sources.
- EIA plant
- 6761 5 generatorsEIA generatorsPlant 6761 G, H, LM3, LM4, LM5
Timeline
- Stated In-service date stated by EIA-860M.
- Observed as announced in EIA-860M (source status: “(P) Planned for installation, but regulatory approvals not initiated”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.
Sources
1 sourceSources EIA-860M
Around this project
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Pivot Solar 42 LLC Under construction | Solar | 19.0 km | 1.9 |