Biomass
- Capacity
- Capacity: sourceNESO · Open license, with creditMW
- Queue position
- PRO-000330-1, PRO-000330-2
- In-service date
- (stated)
- Location
- Penrhos GSP, United Kingdom
Sources
-
View at source →
NESO · 2 records (a0l4L0000005iWNQAY/2, a0l4L0000005iWNQAY/1)
NESO Transmission Entry Capacity (TEC) Register
National Energy SO Open Data Licence v1.0 (based on OGL v3), retrieved 2026-09-12 — free to "exploit the Information commercially and non-commercially"; must "Acknowledge NESO as the source of the Information by including the following attribution statement: Supported by National Energy SO Open Data"
Supported by National Energy SO Open Data · license
Units and requests (2)
How these combine
This project is one site. Each row is one unit or request a register lists for it: a generator in EIA-860M, a stage in NESO’s register, a request in a grid queue. Capacity is the live interconnection requests’ MW added up where there are any, plus any listed generator of a technology no request covers; otherwise the generators’ MW added up. The status is the most advanced any row reports; a withdrawn row ends the project only when no other row carries it on.
| Source | Record | Name | Technology | MW | Status | Proposed COD |
|---|---|---|---|---|---|---|
| NESO Request | a0l4L0000005iWNQAY/1 | Recell at Penrhos (BEGA) | Biomass | 150 | Filed “Scoping” | Oct 30, 2025 |
| NESO Request | a0l4L0000005iWNQAY/2 | Recell at Penrhos (BEGA) | Biomass | 60 | Filed “Scoping” | Oct 31, 2027 |
Report a problem
Sources
Sources NESO
Supported by National Energy SO Open Data