RivertonWILDWOOD DATA CENTER — Under construction · Large load · MO · 8.1 km away
  • Combustion
  • Loads
  • Under construction
  • Size not stated
  • 10 · 100 · 1,000 MW

Gas, combustion turbine

Capacity
Capacity: sourceEIA-860M · Open licenseMW
In-service date
(stated)
Location
Cherokee County, Kansas

Details

Who’s behind it

Developer
Empire District Electric Co · part of Algonquin Power & Utilities CorpOwnership claimOwnership link recorded from its source; no date stated by the source.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Kind
Generation
Technology
Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
Capacity (MW)
27 Capacity is the sum of the 2 generators listed under Sources.
EIA plant
1239 2 generatorsEIA generatorsPlant 1239 13, 14

Timeline

  • Observed as under construction in EIA-860M (source status: “(TS) Construction complete, but not yet in commercial operation”).
  • EIA-860M Preliminary Monthly Electric Generator Inventory: Proposed cod 2026-09-01 → 2026-10-01.
  • Stated In-service date stated by EIA-860M.

“Stated” dates are the source’s plan, not a commitment.

About these dates

Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.

Sources

1 source

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Every source and license · Attribution

View at source

Report a problem

Around this project

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
WILDWOOD DATA CENTER Under construction Large load 8.1 km