Sandrift Storage 2
Storage
As filed: SANDRIFT STORAGE 2
- Capacity
- Capacity: sourceCAISO · Open license, with creditMW
- Queue position
- 2041
- In-service date
- (stated)
- Location
- RIVERSIDE County, California (exact site not public)
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Storage
- Connects at
- Red Bluff Substation 230kVConnection point1,067 MW active (4 of 17 projects).
At this site
2 records at SANDRIFT STORAGE 1At this siteGrouped by the same grid connection point and project name. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | SANDRIFT STORAGE 1 | Storage | 250 | Contracted |
| Another phase high confidence | SANDRIFT STORAGE 2 this record | Storage | 250 | Contracted |
Also at this interconnection point (15)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- ATHOS POWER PLANT Solar + storage, 450 MW, contracted at Red Bluff Substation 230kV
- SAPPHIRE SOLAR Solar + storage, 117 MW, contracted at Red Bluff Substation 230kV
- ALMASOL Solar + storage, 457 MW, built at Red Bluff Substation 230kV
- DESERT SUNLIGHT PV II Solar + storage, 300 MW, built at Red Bluff Substation 230kV
- DESERT SUNLIGHT PV I Solar + storage, 250 MW, built at Red Bluff Substation 230kV
- VICTORY PASS SOLAR Solar + storage, 200 MW, built at Red Bluff Substation 230kV
- DESERT HARVEST Solar + storage, 150 MW, built at Red Bluff Substation 230kV
- EAGLE MOUNTAIN PUMP STORAGE #2 Hydro, 1,400 MW, withdrawn at Red Bluff Substation 230kV
- EAGLE MOUNTAIN PUMP STORAGE #3 Hydro, 1,400 MW, withdrawn at Red Bluff Substation 230kV
- DESERT SUNLIGHT PV III Solar, 500 MW, withdrawn at Red Bluff Substation 230kV
- JUPITER SOLAR Solar, 250 MW, withdrawn at Red Bluff Substation 230kV
- LOMA VERDE SOLAR ENERGY PARK Solar, 170 MW, withdrawn at Red Bluff Substation 230kV
- SIDEWINDER SOLAR Solar, 118.5 MW, withdrawn at Red Bluff Substation 230kV
- NRG RED BLUFF SOLAR 1 (FKA NRG BLYTHE SOLAR 2) Solar, 1 MW, withdrawn at Red Bluff Substation 230kV
- HOLLY RANCH Solar, 0.5 MW, withdrawn at Red Bluff Substation 230kV
Sources CAISO
Timeline
- Stated In-service date stated by CAISO.
- Observed as contracted in CAISO.
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources CAISO