Show on map
- Loads
- In development
- Size not stated
- 10 · 100 · 1,000 MW
Map
- Loads
- In development
- Size not stated
Sediver: the source's site coordinate and 1 exact-grade project within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Sediver
Gas, combined cycle
Key facts
Gas, combined cycle Postponed (source status: Canceled or Postponed) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Interconnection queue
- Duke Energy Carolinas (DUK)
- Location
- York County, South Carolina
Details
Who’s behind it
- Developer
- Central Electric Power
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
- Capacity (MW)
- 520 Capacity is the sum of the 3 generators listed under Sources.
- EIA plant
- 7957 3 generatorsEIA generatorsPlant 7957 CT2A, CT2B, ST1S
Timeline
- Observed as postponed in EIA-860M (source status: “Canceled or Postponed”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.
Sources
1 sourceSources EIA-860M
Around this project
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| QTS-CLT1-DC2 Crane Filed | Large load | 6.8 mi |
Sources FAA OE/AAA