Snowflake A Solar and BESS
  • Wind & solar
  • In development
  • 10 · 100 · 1,000 MW

Snowflake A Solar and BESS

Solar + storage

Capacity
Capacity: sourceEIA-860M · Open licenseMW
Interconnection queue
Arizona Public Service (AZPS)
In-service date
(stated)
Location
Navajo County, Arizona

Sources

  • EIA-860M · 2 records (69060-SNFBA, 69060-SNFA)

    EIA-860M Preliminary Monthly Electric Generator Inventory

    Open license · retrieved Nov 4, 2026

    US federal work — public domain

    View at source →
Units and requests (2)
Units and requests that make up this project
SourceRecordNameTechnologyMWStatusProposed COD
EIA-860M Generator 69060-SNFBA Snowflake A Solar and BESS Storage 475 Filed “(L) Regulatory approvals pending. Not under construction” Aug 1, 2027
EIA-860M Generator 69060-SNFA Snowflake A Solar and BESS Solar 475 Filed “(L) Regulatory approvals pending. Not under construction” Aug 1, 2027
Report a problem
What is wrong with Snowflake A Solar and BESS?

Up to 2,000 characters. A link to a source helps an editor check it.

Only if you would like a reply. It is used for this report and nothing else; see the privacy notice.

Sources

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution

View at source