Spalding Energy Expansion
Gas, combustion turbine
Key facts
Gas, combustion turbine Permitted (source status: Consents Approved) (what this status means)- Capacity
- Capacity: sourceNESO · Open license, with creditMW
- Queue position
- PRO-000249-2
- In-service date
- (stated)
- Location
- Spalding North 400kV Substation, United Kingdom
Details
Who’s behind it
- Developer
- Spalding Energy Expansion Limited
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Kind
- Generation
- Technology
- Gas, combustion turbine source: “Energy Storage System;OCGT (Open Cycle Gas Turbine)”
- Connects at
- Spalding North 400kV SubstationConnection point550 MW active (1 of 3 projects).
At this site
2 records at Spalding Energy ExpansionAt this siteGrouped by the same grid connection point and developer. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | Spalding Energy Expansion this record | Gas, combustion turbine | 550 | Permitted |
| Operating plant being expanded medium confidence | Spalding Energy Expansion | Gas, combustion turbine | 300 | Built |
Also at this interconnection point (1)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- Spalding Gas, combined cycle, 950 MW, built at Spalding North 400kV Substation
Sources NESO
Supported by National Energy SO Open Data
Timeline
- Stated In-service date stated by NESO.
- Observed as permitted in NESO (source status: “Consents Approved”).
“Stated” dates are the source’s plan, not a commitment.
About these dates
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources NESO