Show on map
TX Dallas 7750 Dynasty DriveQTS - DFW 3 - DC1 — Filed · Large load · TX · 4.7 mi awaySTACK DFW02A (Lancaster data centre) — Under construction · Large load · TX · 4.9 mi awayStream Fir Data Center — Filed · Large load · TX · 5.7 mi awayMEI Temporary Crane (Lancaster data centre) — Filed · Large load · TX · 5.8 mi awayQTS Data Centers 6 and 7 — Filed · Large load · TX · 5.9 mi awayLANCASTER DATA CENTER — Under construction · Large load · TX · 5.9 mi awayDatabank 13 — Filed · Large load · TX · 7.8 mi awayDatabank Red Oak Campus - DFW 11 — Filed · Large load · TX · 8.1 mi awayCC6800 - Mustang RED2 (Red Oak data centre) — Filed · Large load · TX · 8.4 mi awayEmerald Hill Energy Storage — Postponed · Storage · TX · 250 MW · 8.6 mi awayALAMO MISSION — Built · Large load · TX · 8.7 mi awayCedar Hill ESS — Filed · Storage · TX · 10 MW · 10.2 mi awayEQUINIX N STEMMONS FREEWAY DALLAS — Built · Large load · TX · 10.9 mi awayMalala — Postponed · Storage · TX · 200 MW · 12.2 mi awayEXXONMOBIL DALLAS DATA CENTER — Built · Large load · TX · 12.3 mi awayDA12 (Dallas data centre) — Under construction · Large load · TX · 13.2 mi awayDolomite Storage — Filed · Storage · TX · 125.7 MW · 13.6 mi away
  • Wind & solar
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

TX Dallas 7750 Dynasty Drive

Solar

Capacity
Capacity: sourceEIA-860M · Open licenseMW
In-service date
(stated)
Location
Dallas County, Texas

Details

Who’s behind it

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Kind
Generation
Technology
Solar source: “Solar Photovoltaic”
EIA plant
66516 generator 19500

Timeline

  • Stated In-service date stated by EIA-860M.
  • Observed as under construction in EIA-860M (source status: “(TS) Construction complete, but not yet in commercial operation”).
  • EIA-860M Preliminary Monthly Electric Generator Inventory: Proposed cod 2026-09-01 → 2026-12-01.
About these dates

“Stated” dates are the source’s plan, not a commitment.

Status and dates as the source last listed them. Later changes follow as we see them.

Sources

1 source

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Every source and license · Attribution

View at source

Report a problem

Around this project

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
QTS - DFW 3 - DC1 Filed Large load 4.7 mi
STACK DFW02A (Lancaster data centre) Under construction Large load 4.9 mi
Stream Fir Data Center Filed Large load 5.7 mi
MEI Temporary Crane (Lancaster data centre) Filed Large load 5.8 mi
QTS Data Centers 6 and 7 Filed Large load 5.9 mi
LANCASTER DATA CENTER Under construction Large load 5.9 mi
Databank 13 Filed Large load 7.8 mi
Databank Red Oak Campus - DFW 11 Filed Large load 8.1 mi
CC6800 - Mustang RED2 (Red Oak data centre) Filed Large load 8.4 mi
Emerald Hill Energy Storage Postponed Storage 8.6 mi 250
ALAMO MISSION Built Large load 8.7 mi
Cedar Hill ESS Filed Storage 10.2 mi 10
EQUINIX N STEMMONS FREEWAY DALLAS Built Large load 10.9 mi
Malala Postponed Storage 12.2 mi 200
EXXONMOBIL DALLAS DATA CENTER Built Large load 12.3 mi
DA12 (Dallas data centre) Under construction Large load 13.2 mi
Dolomite Storage Filed Storage 13.6 mi 125.7

Sources FAA OE/AAA · EPA ICIS-NPDES · EIA-860M · EPA ICIS-Air · ERCOT

Sources