Show on map
Waste Management Tri-Cities LFGTEFremont CA AutoFactory — Under construction · Solar · CA · 3.8 MW · 2.3 mi away7999 Gateway Solar — Under construction · Solar · CA · 4.6 MW · 3.4 mi awayGateway#1&2 (Newark CA) — Announced · Solar · CA · 1.1 MW · 5.1 mi awaySJC02 & SJC03 DATA CENTER — Large load · CA · 6.1 mi away888 Ross Data Center — Filed · Large load · CA · 7.2 mi awayEDGECORE DATA CENTER MECP1 SANTA CLARA 1 PROJECT — Large load · CA · 7.9 mi awayEdgecore -3580 — Filed · Large load · CA · 7.9 mi awaySV8 DATA CENTER — Large load · CA · 8.3 mi awayLBA Data Center West — Filed · Large load · CA · 8.5 mi awayKifer BESS 1 — Under construction · Storage · CA · 50 MW · 8.6 mi awayVANTAGE DATA CENTERS MANAGEMENT CO , LLC — Large load · CA · 8.6 mi away4054 Digital Realty — Built · Large load · CA · 8.8 mi awayPRIME DATA CENTERS — Built · Large load · CA · 9.1 mi away1200 Memorex Skybox Data Center — Filed · Large load · CA · 9.3 mi awaySKYBOX DATA CENTER — Built · Large load · CA · 9.5 mi awayHAYWARD DATA CENTER — Large load · CA · 11.3 mi awayDC-N (San Jose data centre) — Filed · Large load · CA · 11.9 mi awayData Center — Filed · Large load · CA · 12.8 mi away
  • Wind & solar
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Stage not stated
  • Size not stated
  • 10 · 100 · 1,000 MW

Waste Management Tri-Cities LFGTE

Biomass

Capacity
Capacity: sourceEIA-860M · Open licenseMW
Location
Alameda County, California

Details

Who’s behind it

Developer
WM Renewable Energy LLC · part of Waste Management IncOwnership claimOwnership link recorded from its source; no date stated by the source.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Kind
Generation
Technology
Biomass source: “Landfill Gas”
Capacity (MW)
4.8 Capacity is the sum of the 3 generators listed under Sources.
EIA plant
57164 3 generatorsEIA generatorsPlant 57164 GEN1, GEN2, GEN3

Timeline

  • Observed as postponed in EIA-860M (source status: “Canceled or Postponed”).

“Stated” dates are the source’s plan, not a commitment.

About these dates

Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.

Sources

1 source

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Every source and license · Attribution

View at source

Report a problem

Around this project

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Fremont CA AutoFactory Under construction Solar 2.3 mi 3.8
7999 Gateway Solar Under construction Solar 3.4 mi 4.6
Gateway#1&2 (Newark CA) Announced Solar 5.1 mi 1.1
SJC02 & SJC03 DATA CENTER Unknown Large load 6.1 mi
888 Ross Data Center Filed Large load 7.2 mi
EDGECORE DATA CENTER MECP1 SANTA CLARA 1 PROJECT Unknown Large load 7.9 mi
Edgecore -3580 Filed Large load 7.9 mi
SV8 DATA CENTER Unknown Large load 8.3 mi
LBA Data Center West Filed Large load 8.5 mi
Kifer BESS 1 Under construction Storage 8.6 mi 50
VANTAGE DATA CENTERS MANAGEMENT CO , LLC Unknown Large load 8.6 mi
4054 Digital Realty Built Large load 8.8 mi
PRIME DATA CENTERS Built Large load 9.1 mi
1200 Memorex Skybox Data Center Filed Large load 9.3 mi
SKYBOX DATA CENTER Built Large load 9.5 mi
HAYWARD DATA CENTER Unknown Large load 11.3 mi
DC-N (San Jose data centre) Filed Large load 11.9 mi
Data Center Filed Large load 12.8 mi

Sources EIA-860M · EPA ICIS-NPDES · FAA OE/AAA · CAISO · EPA ICIS-Air

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • EPA ICIS-NPDESOpen license · retrieved Nov 16, 2026
  • FAA OE/AAAOpen license · retrieved Nov 16, 2026
  • CAISOOpen license, with credit · retrieved Nov 17, 2026Source: California ISO
  • EPA ICIS-AirOpen license · retrieved Nov 16, 2026