Yaupon Solar Project (Hybrid)
- Wind & solar
- Under construction
- 10 · 100 · 1,000 MW
Map
- Wind & solar
- Under construction
Yaupon Solar Project (Hybrid): the source's site coordinate. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Yaupon Solar Project (Hybrid)
Solar + storage
- Capacity
- Capacity: sourceERCOT · Open licenseMW
- Queue position
- 24INR0042, 24INR0169
- In-service date
- (stated)
- Location
- Milam County, Texas
Sources
-
View at source →
ERCOT · 2 records (24INR0042, 24INR0169)
ERCOT GIS Report (Generator Interconnection Status)
ERCOT Website User Agreement clause 5, retrieved 2026-09-12 — "raw data provided in public portions of this website may be used, reproduced, and redistributed in compilations, charts, and analyses without maintaining such notices"
-
View at source →
EIA-860M · 2 records (66216-SOL, 66216-BESS)
EIA-860M Preliminary Monthly Electric Generator Inventory
US federal work — public domain
Units and requests (4)
How these combine
This project is one site. Each row is one unit or request a register lists for it: a generator in EIA-860M, a stage in NESO’s register, a request in a grid queue. Capacity is the live interconnection requests’ MW added up where there are any, plus any listed generator of a technology no request covers; otherwise the generators’ MW added up. The status is the most advanced any row reports; a withdrawn row ends the project only when no other row carries it on.
| Source | Record | Name | Technology | MW | Status | Proposed COD |
|---|---|---|---|---|---|---|
| ERCOT Request | 24INR0042 | Yaupon Solar SLF | Solar | 200.8 | Built “Completed” | Nov 18, 2026 |
| ERCOT Request | 24INR0169 | Yaupon Storage SLF | Storage | — | Contracted “Completed” | Jul 1, 2028 |
| EIA-860M Generator | 66216-SOL | Yaupon Solar Project (Hybrid) | Solar | 200 | Under construction “(TS) Construction complete, but not yet in commercial operation” | Sep 1, 2026 |
| EIA-860M Generator | 66216-BESS | Yaupon Solar Project (Hybrid) | Storage | 100 | Announced “(P) Planned for installation, but regulatory approvals not initiated” | Dec 1, 2027 |