Kickstart Energy Storage III

Site of 2 records

Company Kickstart Infrastructure LLC

Lead filing
Kickstart Energy Storage III
Grouped by
the same grid connection point and developer
Active (MW)
2.9 across 2
Built (MW)
0 across 0
Withdrawn or canceled (MW)
0 across 0
EIA plant ID
—
Connects at
Tap 345 kV #1906 VENUS_S5 to #68091 NAVARRO
Operating plant
—

1. Records at this site

Records at this site: the lead first; each EIA plant's units follow its first unit; every other record with its relationship to the lead, its confidence, technology, capacity, status and company.
RelationshipConfidenceNameTechnologyMWStatusCompany
Lead filing — Kickstart Energy Storage III Storage 1.4 Studied Kickstart Infrastructure LLC
Another phase high Kickstart Energy Storage IV Storage 1.4 Studied Kickstart Infrastructure LLC

2. Also at this interconnection point

None recorded.

3. Sources

Sources ERCOT

Sources

  • ERCOTTerms of use · retrieved Nov 4, 2026