Show on map
Adrian — Power plant · Oil · Adrian Public Utilities CommElk Creek Solar — Solar · MN · 80 MW · 13.5 km away
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2005
Net generation, 2025
12 MWh
Grid
4 kV to Adrian Public Utilities Comm (SWPP)
Location
Nobles County, Minnesota
Operated by
Adrian Public Utilities CommSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2002 to 2025
Fuel burned MMBtu by year, 2002 to 2025
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
21 years since 2005
Unused energy
18 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
6,500 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
MRO
Report year
2025
Grid voltage kv
4.20
Transmission owner
Adrian Public Utilities Comm
Balancing authority code
SWPP
Balancing authority name
Southwest Power Pool
Fuel burned (MMBtu), 202578
Capacity factor, 20250.001
Heat rate (Btu/kWh), 20256,500
Net generation (MWh), 202512
Balancing authority codeSWPP

Timeline

  • In service · EIA-860M

Sources

3 sources

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Elk Creek Solar Postponed Solar 13.5 km 80

Sources EIA-860M

Sources

Attribution