- Bioenergy
- Retired
- 10 · 100 · 1,000 MW
Map
- Bioenergy
- Retired
Aliso Water Management Agency: location and 3 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Aliso Water Management Agency
Power plant · Biomass
Key facts
Power plant · Biomassran 0% of 2015 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1997
- Net generation, 2015
- 6 MWh
- Location
- Orange County, California
- Operated by
- South Orange Co Wastewtr AuthSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
- Gas
- Biomass and waste
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Biomass source: “Other Waste Biomass”
- Age
- 29 years since 1997
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | CISO |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- December 2016
- First unit retired
- June 2016
- Capacity retired
- 1.2 MW
- Generators retired
- 3
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GEN3 | Other Waste Biomass | 0.4 MW | Retired | June 2016 |
| GEN1 | Other Waste Biomass | 0.4 MW | Retired | December 2016 |
| GEN2 | Other Waste Biomass | 0.4 MW | Retired | December 2016 |
Grid
EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).- Balancing authority
- CISO
Transmission lines within 15 mi (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Units GEN1, GEN2 scheduled to retire, 0.8 MW · EIA-860M
- Stated Unit GEN3 scheduled to retire, 0.4 MW · EIA-860M
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Hybrid Holdings 1 Capistrano Postponed | Storage | 3.2 mi | 4 |
| Margarita Energy Center Postponed | Gas, combustion turbine | 4.6 mi | 48.2 |
| Santa Ana Storage 3 Postponed | Storage | 14.9 mi | 40 |
Sources EIA-860M