Show on map
Aliso Water Management Agency — Power plant · Biomass · South Orange Co Wastewtr Auth
  • Bioenergy
  • Retired
  • 10 · 100 · 1,000 MW

Aliso Water Management Agency

Power plant · Biomass

Key facts

Power plant · Biomassran 0% of 2015 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1997
Net generation, 2015
6 MWh
Location
Orange County, California
Operated by
South Orange Co Wastewtr AuthSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2015
6MWh
Fuel burned, 2015
113MMBtu
Capacity factor, 2015
0.1%
Heat rate, 2015
18,833Btu/kWh
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
2016 (6 of 12 months)684—14,000
201561130.1%18,833
20146820.1%13,667
20136,17485,02458.7%13,771
20126740.1%12,333
20117960.1%13,714
20106,42597,05861.1%15,106
20096,09884,12758.0%13,796
20086,47078,35261.4%12,110
20076,44673,80061.3%11,449
20066,50875,40061.9%11,585
20056,67878,89463.5%11,814
20046,93482,70965.8%11,929
20036,84958,52965.1%8,546
20025,44160,66751.8%11,150
20016,80073,22064.7%10,768
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

2 sources

Sources EIA-860M · EIA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)

Every source and license · Attribution

View at source