Big Bend: location and 6 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Big Bend
Power plant · Gas, combined cycle
Key facts
Power plant · Gas, combined cycleran 47% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1970
- Net generation, 2025
- 7,473,386 MWh
- Grid
- 230 kV to Tampa Electric Co (TEC)
- Location
- Hillsborough County, Florida
- Operated by
- Tampa Electric Co
Output
- Gas
- Coal
- Oil
Details
Who’s behind it
- Owner
- TECO Energy Inc
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
- Age
- 56 years since 1970
- Unused energy
- 8,268 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 7,020 Btu/kWh 2025
All 7 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| EPA greenhouse gas reporting (GHGRP) |
|
| Fuel burned (MMBtu), 2025 | 52,463,697 |
| Capacity factor, 2025 | 0.475 |
| Heat rate (Btu/kWh), 2025 | 7,020.1 |
| Net generation (MWh), 2025 | 7,473,386.0 |
| Balancing authority code | TEC |
Solar arrays
Solar arrays
The array area counts panels and inverters only, not buildings, fences or the whole site.
USGS maps the center of this array 1.6 km from the point this page maps the plant at.
- Array area (acres)
- 82.7
- AC capacity (MW)
- 19
- DC capacity (MW)
- 23
- Mounting
- Single-axis tracking
- Site type
- Greenfield
- Began operating
- 2017
Source USPVDB
Source
- U.S. Large-Scale Solar Photovoltaic DatabaseMap services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
Retirement
EIA-860M September 2026StatusSome generators are scheduled to retire; most of the plant's capacity is not, so it is shown as operating. As of EIA-860M for September 2026.- Capacity retired
- 1,066.4 MW
- Generators retired
- 5
- Next scheduled retirement
- January 2040
- Capacity scheduled to retire
- 486 MW
- Generators scheduled to retire
- 1
- Share of in-service capacity scheduled
- 27%
- Capacity still in service
- 1,797 MW
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GT1 | Petroleum Liquids | 18 MW | Retired | December 2008 |
| GT2 | Petroleum Liquids | 78.7 MW | Retired | December 2008 |
| GT3 | Petroleum Liquids | 78.7 MW | Retired | December 2008 |
| ST2 | Conventional Steam Coal | 445.5 MW | Retired | December 2021 |
| ST3 | Natural Gas Steam Turbine | 445.5 MW | Retired | April 2023 |
| ST4 | Natural Gas Steam Turbine | 486 MW | Scheduled to retire | January 2040 |
By technology
| Technology | Retired | Scheduled to retire |
|---|---|---|
| Natural Gas Steam Turbine | 445.5 MW | 486 MW |
| Conventional Steam Coal | 445.5 MW | |
| Petroleum Liquids | 175.4 MW |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 230 kV
- Transmission or distribution system owner
- Tampa Electric Co
- Balancing authority
- Tampa Electric Company
- NERC region
- SERC
Transmission lines within 25 km (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Tampa Electric Co | Operator | EIA-860M | ||
| TECO ENERGY INC | Owner | 100.0% | 31 Dec 2023 | EPA GHGRP |
Timeline
- Stated Unit ST4 scheduled to retire, 486 MW · EIA-860M
- Stated Unit ST3 scheduled to retire, 445.5 MW · EIA-860M
- Stated Unit ST2 scheduled to retire, 445.5 MW · EIA-860M
- Stated Units GT1, GT2, GT3 scheduled to retire, 175.4 MW · EIA-860M
- In service · EIA-860M
Sources
7 sourcesSources EIA-860M · GEM · LBNL · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- U.S. Large-Scale Solar Photovoltaic Database (USPVDB) — USGS and LBNL; one row per facility with its array footprintMap services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Big Bend III Battery Storage Permitted | Storage | 0.1 km | 75 |
| Tampa Electric Co NA 3 Postponed | Gas, combustion turbine | 0.5 km | 99 |
| H L Culbreath Bayside Power Station Postponed | Gas, combustion turbine | 12.7 km | 503.8 |
| Tampa Electric Co NA 2 Postponed | Gas, combustion turbine | 12.7 km | 982 |
| South Tampa Energy Storage Postponed | Storage | 13.3 km | 20 |
| Keene Branch Solar Under construction | Solar | 20.3 km | 74.5 |