Show on map
Breese — Power plant · Oil · City of Breese - (IL)Trenton CSG 1 LLC — Solar · IL · 5 MW · 14.3 km away
  • Combustion
  • Wind & solar
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1953
Net generation, 2025
539 MWh
Grid
12 kV to City of Breese - (IL) (MISO)
Location
Clinton County, Illinois
Operated by
City of Breese - (IL)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
73 years since 1953
Unused energy
148 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
13,043 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Eia status
By code
OP
Mw
13
Units
5
SB
Mw
3.90
Units
2
Standby mw
3.90
Status rule
some_units_retired
In service mw
16.90
Out of service mw
0
Fuel burned (MMBtu), 20257,030
Capacity factor, 20250.004
Heat rate (Btu/kWh), 202513,042.7
Net generation (MWh), 2025539
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
2 MW
Generators retired
1
Capacity still in service
16.9 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
ST2Petroleum Liquids2 MWRetiredJanuary 2003

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
12 kV
Transmission or distribution system owner
City of Breese - (IL)
Balancing authority
Midcontinent Independent Transmission System Operator, Inc..
NERC region
SERC
Transmission lines within 25 km (4)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit ST2 scheduled to retire, 2 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Trenton CSG 1 LLC Under construction Solar 14.3 km 5

Sources EIA-860M

Sources

Attribution