Breese — Power plant · Oil · City of Breese - (IL)
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1953
Net generation, 2025
539 MWh
Grid
12 kV to City of Breese - (IL) (MISO)
Location
Clinton County, Illinois
Operated by
City of Breese - (IL)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Operations

Net generation, 2025
539MWh
Fuel burned, 2025
7,030MMBtu
Capacity factor, 2025
0.4%
Heat rate, 2025
13,043Btu/kWh
Capacity factor % of full output, by year
Heat rate Btu per kWh, by year
Net generation, fuel burned, capacity factor and heat rate by year, newest first, as EIA's bulk electricity file states them.
YearNet generation (MWh)Fuel burned (MMBtu)Capacity factorHeat rate (Btu/kWh)
20255397,0300.4%13,043
20242634,2760.2%16,259
20232648,1650.2%—
20223664,3280.2%11,825
20217919,4810.5%11,986
20204483,5210.3%7,859
20192883,8000.2%13,194
20182723,2930.2%12,107
20173173,7250.2%11,751
20164475,2380.3%11,718
20152253,2920.1%14,631
20142083,3860.1%16,279
20132413,1920.2%13,245
20122933,4660.2%11,829
20112663,0630.2%11,515
20102833,2860.2%11,611
20093173,8270.2%12,073
20083825,2870.3%13,840
20073074,5150.2%14,707
20064635,6500.3%12,203
20051,25317,2030.9%13,729
20043664,3630.2%11,921
20034354,9250.3%11,322
20023553,8730.2%10,910
20013433,7540.2%10,945
How these are worked out

Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.

Sources

2 sources

Sources EIA-860M · EIA

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026