Broad Mountain
Power plant · Biomass
Key facts
Power plant · Biomassran 46% of 2022 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2009
- Net generation, 2022
- 44,130 MWh
- Location
- Schuylkill County, Pennsylvania
- Operated by
- Hunlock Creek Generating, LLC
Output
- Biomass and waste
Details
Who’s behind it
- Owner
- UGI Corp
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Biomass source: “Landfill Gas”
- Age
- 17 years since 2009
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| EPA greenhouse gas reporting (GHGRP) |
|
| Balancing authority code | PJM |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- October 2023
- Capacity retired
- 11 MW
- Generators retired
- 2
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GEN1 | Landfill Gas | 5.5 MW | Retired | October 2023 |
| GEN2 | Landfill Gas | 5.5 MW | Retired | October 2023 |
Grid
EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).- Balancing authority
- PJM
Transmission lines within 15 mi (4)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Hunlock Creek Generating, LLC | Operator | EIA-860M | ||
| UGI CORP | Owner | 100.0% | Dec 31, 2023 | EPA GHGRP |
Timeline
- Stated Units GEN1, GEN2 scheduled to retire, 11 MW · EIA-860M
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Good Spring NGCC Facility Postponed | Gas, combined cycle | 5.3 mi | 358 |
| WMPI Pty LLC Postponed | Coal | 8.5 mi | 41 |