Show on map
Butter Creek Power LLC — Power plant · Wind · CR51 Inc.Perennial Wind Chaser Station — Postponed · Gas, combustion turbine · OR · 424 MW · 7.3 mi awaySunstone Solar — Filed · Solar + storage · OR · 2,400 MW · 9.5 mi awayPDX 245 Campus-Water Tank/Auxiliary Buidling — Filed · Large load · OR · 10.5 mi awayAMAZON DATA SERVICES, INC. — Built · Large load · OR · 10.7 mi awayTutuilla Solar — Under construction · Solar · OR · 1.6 MW · 13.6 mi awayWheatridge Optimization I — Under construction · Solar + storage · OR · 175 MW · 13.8 mi awayWheatridge Optimization II — Under construction · Solar + storage · OR · 190 MW · 14.0 mi away
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Butter Creek Power LLC

Power plant · Wind

Key facts

Power plant · Windran 22% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2009
Net generation, 2025
9,704 MWh
Grid
69 kV to PacifiCorp (PACW)
Location
Umatilla County, Oregon
Operated by
CR51 Inc.

Output

Net generation MWh by year, 2009 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Wind source: “Onshore Wind Turbine”
Age
17 years since 2009
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100001019718
Location id
L100001017729
Eia plant ids
56967
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
69
Transmission owner
PacifiCorp
Balancing authority code
PACW
Balancing authority name
PacifiCorp - West
Fuel burned (MMBtu), 202533,110
Capacity factor, 20250.222
Net generation (MWh), 20259,704
Balancing authority codePACW

Wind turbines

Turbines
3
Turbine capacity (MW)
5
Turbine models
3 Vestas V82-1.65
Hub height (m)
80
Rotor diameter (m)
82
Year online
2009

Source U.S. Wind Turbine Database

Source

  • U.S. Wind Turbine DatabaseOpen license · retrieved Oct 25, 2026Map services and data are available from U.S. Wind Turbine Database, provided by the U.S. Geological Survey, American Clean Power Association, and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uswtdb

Attribution

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
CR51 Inc. Operator EIA-860M
Butter Creek Power, LLC Owner 100.0% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · U.S. Wind Turbine Database · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Perennial Wind Chaser Station Postponed Gas, combustion turbine 7.3 mi 424
Sunstone Solar Filed Solar + storage 9.5 mi 2,400
PDX 245 Campus-Water Tank/Auxiliary Buidling Filed Large load 10.5 mi
AMAZON DATA SERVICES, INC. Built Large load 10.7 mi
Tutuilla Solar Under construction Solar 13.6 mi 1.6
Wheatridge Optimization I Under construction Solar + storage 13.8 mi 175
Wheatridge Optimization II Under construction Solar + storage 14.0 mi 190

Sources EIA-860M · FAA OE/AAA · EPA ICIS-Air

Sources

Attribution