Show on map
- Combustion
- In development
- Operating
- 10 · 100 · 1,000 MW
Map
- Combustion
- In development
- Operating
Caledonia: location and 1 exact-grade project within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Caledonia
Power plant · Gas, combined cycle
Key facts
Power plant · Gas, combined cycleran 75% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2003
- Net generation, 2025
- 5,246,915 MWh
- Grid
- 500 kV to Tennessee Valley Authority (TVA)
- Location
- Lowndes County, Mississippi
- Operated by
- Tennessee Valley Authority
Output
- Gas
Details
Who’s behind it
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
- Age
- 23 years since 2003
- Unused energy
- 1,770 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 6,988 Btu/kWh 2025
All 8 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Grid |
|
| EPA greenhouse gas reporting (GHGRP) |
|
| Fuel burned (MMBtu), 2025 | 36,666,571 |
| Capacity factor, 2025 | 0.748 |
| Heat rate (Btu/kWh), 2025 | 6,988.2 |
| Net generation (MWh), 2025 | 5,246,915 |
| Balancing authority code | TVA |
Ownership
3 companies3| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Tennessee Valley Authority | Operator | EIA-860M | ||
| U.S. Government | Owner | 31 Dec 2023 | EPA GHGRP | |
| GE Energy Financial Services | Owner | 100.0% | 31 Dec 2025 | EIA-860 |
Timeline
- In service · EIA-860M
Sources
6 sourcesSources EIA-860M · GEM · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT) · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| New Caledonia Announced | Gas, combustion turbine | 4.0 km | 504 |