Carver — Power plant · Solar · Captona Carver LLCSolar Carver 3 Hybrid — Solar + storage · MA · 2 MW · 8.6 km awaySolar Carver 1 Hybrid — Solar + storage · MA · 4 MW · 10.9 km awayLogging Swamp North — Solar · MA · 5 MW · 16.9 km awayLogging Swamp South — Solar · MA · 5 MW · 17.0 km awayBraley Hill North Solar — Solar + storage · MA · 10 MW · 17.7 km awaySnipatuit Road Solar — Solar + storage · MA · 8 MW · 17.7 km awayFeatherbed Lane South Solar — Solar + storage · MA · 2 MW · 18.9 km awayCushman Road Solar — Solar + storage · MA · 6 MW · 21.3 km awayClems Way Solar — Solar · MA · 5 MW · 21.8 km awayMA Acushnet 540R Main St — Solar + storage · MA · 6 MW · 24.7 km awayBlueWave Capital-Mattapoisett (SREC II) — Solar · MA · 4.5 MW · 24.7 km away
  • Wind & solar
  • In development
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Solar

Key facts

Power plant · Solarran 14% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2017
Net generation, 2025
1,822 MWh
Grid
25 kV to Massachusetts Electric Co (ISNE)
Location
Plymouth County, Massachusetts

Output

Net generation MWh by year, 2020 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Solar source: “Solar Photovoltaic”
Age
9 years since 2017
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100000814971
Location id
L100000812348
Eia plant ids
64115
Grid
Nerc region
NPCC
Report year
2025
Grid voltage kv
25
Transmission owner
Massachusetts Electric Co
Balancing authority code
ISNE
Balancing authority name
ISO New England Inc.
Fuel burned (MMBtu), 20256,215
Capacity factor, 20250.139
Net generation (MWh), 20251,822
Balancing authority codeISNE

Solar arrays

Array area (acres)
3.4
AC capacity (MW)
1.5
DC capacity (MW)
1.8
Mounting
Fixed tilt
Site type
Greenfield
Began operating
2017

Source USPVDB

Source

  • U.S. Large-Scale Solar Photovoltaic DatabaseOpen license · retrieved 25 Oct 2026Map services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb

Attribution

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Captona Carver LLC Operator EIA-860M
Captona Partners Solar I Finco LLC Owner 100.0% 31 Dec 2025 EIA-860

Timeline

  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Solar Carver 3 Hybrid Under construction Solar + storage 8.6 km 2
Solar Carver 1 Hybrid Under construction Solar + storage 10.9 km 4
Logging Swamp North Permitted Solar 16.9 km 5
Logging Swamp South Permitted Solar 17.0 km 5
Braley Hill North Solar Under construction Solar + storage 17.7 km 10
Snipatuit Road Solar Under construction Solar + storage 17.7 km 8
Featherbed Lane South Solar Under construction Solar + storage 18.9 km 2
Cushman Road Solar Filed Solar + storage 21.3 km 6
Clems Way Solar Permitted Solar 21.8 km 5
MA Acushnet 540R Main St Filed Solar + storage 24.7 km 6
BlueWave Capital-Mattapoisett (SREC II) Postponed Solar 24.7 km 4.5

Sources EIA-860M

Sources

Attribution