Show on map
- Wind & solar
- Storage
- Loads
- Under construction
- Operating
- Size not stated
- 10 · 100 · 1,000 MW
Map
- Wind & solar
- Storage
- Loads
- Under construction
- Operating
- Size not stated
Cascades: location and 17 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Cascades
Power plant · Solar
Key facts
Power plant · Solarran 16% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2021
- Net generation, 2025
- 2,852 MWh
- Grid
- 1 kV to Public Service Elec & Gas Co (PJM)
- Location
- Middlesex County, New Jersey
- Operated by
- Greenbacker Renewable Energy CorporationSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Solar source: “Solar Photovoltaic”
- Age
- 5 years since 2021
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 9,730 |
| Capacity factor, 2025 | 0.163 |
| Net generation (MWh), 2025 | 2,852 |
| Balancing authority code | PJM |
Solar array
Solar array
The array area counts panels and inverters only, not buildings, fences or the whole site.
- Array area (acres)
- 4.6
- AC capacity (MW)
- 2
- DC capacity (MW)
- 2.6
- Mounting
- Fixed tilt
- Site type
- Greenfield
- Began operating
- 2021
Timeline
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · GEM · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- USPVDBMap services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| BARCLAYS CAPITAL DATA CENTER Built | Large load | 0.3 mi | |
| EVOQUE DATA CENTER SOLUTIONS - PNJ1 Built | Large load | 0.4 mi | |
| NJ 1 DATA CENTER Built | Large load | 1.6 mi | |
| Prologis - SLCNJ001 - Community Solar Under construction | Solar | 2.1 mi | 3.2 |
| FIDESSA Built | Large load | 4.4 mi | |
| MORGAN STANLEY DATA CENTER Built | Large load | 4.7 mi | |
| BPL NJ - Belmont Under construction | Solar | 5.0 mi | 1.8 |
| Milltown Onsite BESS Under construction | Storage | 7.4 mi | 13.2 |
| Middlesex Energy Center LLC Postponed | Gas, combined cycle | 9.4 mi | 570 |
| Gateway Energy Center, LLC Postponed | Gas, combined cycle | 10.0 mi | 440 |
| BARCLAYS CAPITAL DATA CENTER Built | Large load | 10.7 mi | |
| Coreweave Under construction | Large load | 12.5 mi | |
| 50 Meister Ave Under construction | Solar | 13.0 mi | 1.5 |
| BLOOMBERG DATA CENTER Built | Large load | 13.0 mi | |
| Elevate Arthur Kill Under construction | Storage | 13.7 mi | 15.1 |
| BPL NJ - Union Distribution Center Under construction | Solar | 14.2 mi | 1.5 |
| Swiftsure Postponed | Storage | 14.5 mi | 121 |
Sources EPA ICIS-Air · EIA-860M · EPA ICIS-NPDES · FAA OE/AAA