Chillingham Storage — Power plant · Storage · Chillingham Storage LLCChillingham Solar — Solar · TX · 352.4 MW · 0.1 km awayAUS02 DATA CENTER — Large load · TX · 6.0 km awayAUS01 (Temple data centre) — Large load · TX · 6.5 km awayCC2500 - AUS01 Temple TX (Temple data centre) — Large load · TX · 7.6 km awayAUS04 DATA CENTER — Large load · TX · 8.8 km awayHermes Storage BESS — Solar + storage · TX · 200.8 MW · 10.9 km awayLimewood Bell Renewables Solar — Solar + storage · TX · 254.6 MW · 13.8 km awaySypert Branch Solar — Solar · TX · 261.1 MW · 15.6 km awayBig Elm Storage — Storage · TX · 100 MW · 15.7 km awayTEMPLE 5MW DATA CENTER — Large load · TX · 16.2 km awayRosebud Solar, LLC — Solar · TX · 132 MW · 22.3 km awayProject Orion (Burlington data centre) — Large load · TX · 24.1 km awayFREEBIRD DATA CENTER — Large load · TX · 24.2 km awaySB ENERGY - ORION DATA CENTER — Large load · TX · 24.8 km away
  • Wind & solar
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • 10 · 100 · 1,000 MW

Chillingham Storage

Power plant · Storage

Key facts

Power plant · Storage Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2025
Grid
345 kV to Oncor Electric Delivery Company LLC (ERCO)
Location
Bell County, Texas
Operated by
Chillingham Storage LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2025 to 2026

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Storage source: “Batteries”
Age
1 year since 2025
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100001058261
Location id
L100001050517
Eia plant ids
68065
Grid
Nerc region
TRE
Report year
2025
Grid voltage kv
345
Transmission owner
Oncor Electric Delivery Company LLC
Balancing authority code
ERCO
Balancing authority name
Electric Reliability Council of Texas, Inc.
Fuel burned (MMBtu), 20250
Net generation (MWh), 2025-7,905
Balancing authority codeERCO
Data notes (1)
  • Capacity factor, 2025 not shown: net generation -7905.0 MWh is not positive (the plant consumed at least as much as it produced over the year)

Timeline

  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · GEM · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Chillingham Solar Built Solar 0.1 km 352.4
AUS02 DATA CENTER Under construction Large load 6.0 km
AUS01 (Temple data centre) Filed Large load 6.5 km
CC2500 - AUS01 Temple TX (Temple data centre) Filed Large load 7.6 km
AUS04 DATA CENTER Under construction Large load 8.8 km
Hermes Storage BESS Under construction Solar + storage 10.9 km 200.8
Limewood Bell Renewables Solar Under construction Solar + storage 13.8 km 254.6
Sypert Branch Solar Built Solar 15.6 km 261.1
Big Elm Storage Postponed Storage 15.7 km 100
TEMPLE 5MW DATA CENTER Built Large load 16.2 km
Rosebud Solar, LLC Postponed Solar 22.3 km 132
Project Orion (Burlington data centre) Filed Large load 24.1 km
FREEBIRD DATA CENTER Under construction Large load 24.2 km