Disney Prospect: location and 8 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Disney Prospect
Power plant · Gas, other
Key facts
Power plant · Gas, otherran 91% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2017
- Net generation, 2025
- 7,965 MWh
- Grid
- 34 kV to Los Angeles Department of Water & Power (LDWP)
- Location
- Los Angeles County, California
- Operated by
- Bloom Energy
Output
- Gas
Details
Who’s behind it
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, other source: “Other Natural Gas”
- Age
- 9 years since 2017
- Heat rate
- 7,152 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 56,963 |
| Capacity factor, 2025 | 0.909 |
| Heat rate (Btu/kWh), 2025 | 7,151.7 |
| Net generation (MWh), 2025 | 7,965 |
| Balancing authority code | LDWP |
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Bloom Energy | Operator | EIA-860M | ||
| The Walt Disney Company | Owner | 100.0% | Dec 31, 2025 | EIA-860 |
Timeline
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| AB Van Nuys Announced | Solar | 9.8 mi | 1.6 |
| LATTC South Campus Solar Postponed | Solar | 10.0 mi | 1.1 |
| Scattergood Postponed | Gas, combined cycle | 11.4 mi | 346 |
| PRIME DATA CENTER VERNON Built | Large load | 12.9 mi | |
| 20525 Nordhoff PV (North) Under construction | Solar | 13.5 mi | 1.9 |
| Foothill Solar Project Postponed | Solar | 14.1 mi | 1.1 |
| Van Norman Bypass Solar Project Postponed | Solar | 14.6 mi | 2 |
| Scholl Canyon Under construction | Biomass | 14.7 mi | 12 |
Sources EIA-860M · EPA ICIS-NPDES