- Clean firm
- Operating
- 10 · 100 · 1,000 MW
Map
- Clean firm
- Operating
Eagle Point: location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Eagle Point
Power plant · Hydro
Key facts
Power plant · Hydroran 60% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1957
- Net generation, 2025
- 14,777 MWh
- Grid
- 115 kV to PacifiCorp (PACW)
- Location
- Jackson County, Oregon
- Operated by
- PacifiCorpSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Operations
- Net generation, 2025
- 14,777
MWh - Fuel burned, 2025
- 50,420
MMBtu - Capacity factor, 2025
- 60.2
% - Heat rate, 2025
- Not stated
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2025 | 14,777 | 50,420 | 60.2% | — |
| 2024 | 14,604 | 49,829 | 59.4% | — |
| 2023 | 14,660 | 50,019 | 59.8% | — |
| 2022 | 13,590 | 46,370 | 55.4% | — |
| 2021 | 13,418 | 118,669 | 54.7% | — |
| 2020 | 15,999 | 140,263 | 65.0% | — |
| 2019 | 16,812 | 149,712 | 68.5% | — |
| 2018 | 16,411 | 149,405 | 66.9% | — |
| 2017 | 18,371 | 169,254 | 74.9% | — |
| 2016 | 18,526 | 171,030 | 75.3% | — |
| 2015 | 16,857 | 157,090 | 68.7% | — |
| 2014 | 16,187 | 153,938 | 66.0% | — |
| 2013 | 16,334 | 155,843 | 66.6% | — |
| 2012 | 17,897 | 170,308 | 72.8% | — |
| 2011 | 18,508 | 179,823 | 75.5% | — |
| 2010 | 17,206 | 167,861 | 70.2% | — |
| 2009 | 17,375 | 169,580 | 70.8% | — |
| 2008 | 17,350 | 170,967 | 70.5% | — |
| 2007 | 18,520 | 183,050 | 75.5% | — |
| 2006 | 13,381 | 132,726 | 54.5% | — |
| 2005 | 16,337 | 163,354 | 66.6% | — |
| 2004 | 16,872 | 169,091 | 68.6% | — |
| 2003 | 15,279 | 156,472 | 62.3% | — |
| 2002 | 17,064 | 173,592 | 69.6% | — |
| 2001 | 15,904 | 164,336 | 64.8% | — |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.