Everett Cogen

Power plant · Biomass

Key facts

Power plant · Biomassran 57% of 2010 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1996
Net generation, 2010
211,212 MWh
Grid
115 kV to Snohomish County PUD No 1 (BPAT)
Location
Snohomish County, Washington
Operated by
Kimberly-Clark CorpSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2002 to 2011
Fuel burned MMBtu by year, 2002 to 2011
  • Gas
  • Oil
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Wood/Wood Waste Biomass”
Age
30 years since 1996
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeBPAT

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
October 2011
Capacity retired
42 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Wood/Wood Waste Biomass42 MWRetiredOctober 2011

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
115 kV
Transmission or distribution system owner
Snohomish County PUD No 1
Balancing authority
Bonneville Power Administration
NERC region
WECC
Transmission lines within 15 mi (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit 1 scheduled to retire, 42 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 9, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Arlington Battery Energy Storage System Under construction Storage 12.8 mi 25

Sources EIA-860M