- Combustion
- Storage
- Loads
- In development
- Under construction
- Operating
- Retired
- Stage not stated
- Size not stated
- 10 · 100 · 1,000 MW
Map
- Combustion
- Storage
- Loads
- In development
- Under construction
- Operating
- Retired
- Stage not stated
- Size not stated
Extreme San Ignacio: location and 14 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Extreme San Ignacio
Power plant · Gas, other
Key facts
Power plant · Gas, otherran 22% of 2024 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2019
- Net generation, 2024
- 1,942 MWh
- Grid
- 12 kV to Pacific Gas & Electric Co. (CISO)
- Location
- Santa Clara County, California
- Operated by
- Bloom Energy
Output
- Gas
Details
Who’s behind it
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, other source: “Other Natural Gas”
- Age
- 7 years since 2019
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | CISO |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- June 2024
- Capacity retired
- 1 MW
- Generators retired
- 1
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| EXN02 | Other Natural Gas | 1 MW | Retired | June 2024 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 12 kV
- Transmission or distribution system owner
- Pacific Gas & Electric Co.
- Balancing authority
- California Independent System Operator
- NERC region
- WECC
Transmission lines within 15 mi (10)
Connection points within 15 mi (1)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Bloom Energy | Operator | EIA-860M | ||
| Cresmark Equipment Finance | Owner | 100.0% | Dec 31, 2025 | EIA-860 |
Timeline
- Stated Unit EXN02 scheduled to retire, 1 MW · EIA-860M
- In service · EIA-860M
Sources
6 sourcesSources EIA-860M · LBNL · CAISO · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- CAISOSource: California ISO
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| CHINA MOBILE INTERNATIONAL SAN JOSE DATA CENTER Unknown | Large load | 0.2 mi | |
| Equinix SV-19 - 131 Great Oaks Blvd SJ Filed | Large load | 0.3 mi | |
| Data Center Filed | Large load | 8.5 mi | |
| DC-N (San Jose data centre) Filed | Large load | 9.4 mi | |
| SKYBOX DATA CENTER Built | Large load | 12.6 mi | |
| LBA Data Center West Filed | Large load | 12.9 mi | |
| 1200 Memorex Skybox Data Center Filed | Large load | 12.9 mi | |
| 4054 Digital Realty Built | Large load | 13.0 mi | |
| PRIME DATA CENTERS Built | Large load | 13.2 mi | |
| Kifer BESS 1 Under construction | Storage | 13.3 mi | 50 |
| VANTAGE DATA CENTERS MANAGEMENT CO , LLC Unknown | Large load | 13.9 mi | |
| SV8 DATA CENTER Unknown | Large load | 14.1 mi | |
| Edgecore -3580 Filed | Large load | 14.2 mi | |
| EDGECORE DATA CENTER MECP1 SANTA CLARA 1 PROJECT Unknown | Large load | 14.2 mi |
Sources EPA ICIS-NPDES · FAA OE/AAA · EIA-860M · CAISO · EPA ICIS-Air