Granite: location and 6 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Granite
Power plant · Hydro
Key facts
Power plant · Hydroran 24% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1896
- Net generation, 2025
- 4,219 MWh
- Grid
- 12 kV to PacifiCorp (PACE)
- Location
- Salt Lake County, Utah
- Operated by
- PacifiCorpSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Hydro source: “Conventional Hydroelectric”
- Age
- 130 years since 1896
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 14,394 |
| Capacity factor, 2025 | 0.241 |
| Net generation (MWh), 2025 | 4,219 |
| Balancing authority code | PACE |
Timeline
- In service · EIA-860M
Sources
3 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| CONDUENT DATA CENTER Unknown | Large load | 10.9 km | |
| DATA CENTER (200 S 200 E SLC) Built | Large load | 18.4 km | |
| Project Sequoia- Data Center Filed | Large load | 22.0 km | |
| VAST DATA CENTER Built | Large load | 22.8 km | |
| UTAH DATA CENTER Built | Large load | 24.1 km | |
| ALIGNED DATA CENTER SLC-4 Built | Large load | 24.5 km |