Show on map
Hampden Landfill Solar LLC — Power plant · Storage · Hampden Landfill Solar LLCPalmer Renewable Energy — Postponed · Biomass · MA · 42 MW · 9.6 mi awayStony Brook — Postponed · Gas, combined cycle · MA · 422 MW · 10.9 mi awayWillington Solar One, LLC — Under construction · Solar · CT · 2 MW · 11.9 mi awayChicopee BESS — Under construction · Storage · MA · 5 MW · 13.3 mi awayEllington Solar One — Postponed · Solar · CT · 2 MW · 13.4 mi awayRiverside Holyoke — Postponed · Hydro · MA · 1.1 MW · 13.8 mi awayHadley Falls — Postponed · Hydro · MA · 3.5 MW · 14.7 mi awayHolyoke MA BESS 1 — Under construction · Storage · MA · 5 MW · 14.7 mi away
  • Wind & solar
  • Storage
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Hampden Landfill Solar LLC

Power plant · Storage

Key facts

Power plant · Storageran 4% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2024
Net generation, 2025
1,838 MWh
Grid
13 kV to Massachusetts Electric Co (ISNE)
Location
Hampden County, Massachusetts
Operated by
Hampden Landfill Solar LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2025

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Storage source: “Batteries”
Age
2 years since 2024
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
NPCC
Report year
2025
Grid voltage kv
13.20
Transmission owner
Massachusetts Electric Co
Balancing authority code
ISNE
Balancing authority name
ISO New England Inc.
Fuel burned (MMBtu), 20256,270
Capacity factor, 20250.043
Net generation (MWh), 20251,838
Balancing authority codeISNE

Timeline

  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Palmer Renewable Energy Postponed Biomass 9.6 mi 42
Stony Brook Postponed Gas, combined cycle 10.9 mi 422
Willington Solar One, LLC Under construction Solar 11.9 mi 2
Chicopee BESS Under construction Storage 13.3 mi 5
Ellington Solar One Postponed Solar 13.4 mi 2
Riverside Holyoke Postponed Hydro 13.8 mi 1.1
Hadley Falls Postponed Hydro 14.7 mi 3.5
Holyoke MA BESS 1 Under construction Storage 14.7 mi 5

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution