Harrington — Power plant · Gas, steam turbine · Southwestern Public Service CoProject Matador Gas Plant (PMG) — Under construction · Gas, combined cycle · TX · 11,679.3 MW · 16.3 km awayProject Matador Nuclear — Announced · Nuclear · TX · 4,468 MW · 16.3 km awayMajestic 2 Wind Farm — Postponed · Wind · TX · 79.2 MW · 18.0 km away
  • Combustion
  • Clean firm
  • In development
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Gas, steam turbine

Key facts

Power plant · Gas, steam turbineran 21% of 2025 Retiring
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1976
Net generation, 2025
2,018,141 MWh
Grid
230 kV to Southwestern Public Service Co (SWPP)
Location
Potter County, Texas

Output

Net generation MWh by year, 2001 to 2026
Fuel burned MMBtu by year, 2001 to 2026
  • Gas
  • Coal

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, steam turbine source: “Natural Gas Steam Turbine”
Age
50 years since 1976
Heat rate
11,070 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110071161389
Subparts reported
D
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1001042
Fuel burned (MMBtu), 202522,341,268
Capacity factor, 20250.213
Heat rate (Btu/kWh), 202511,070.2
Net generation (MWh), 20252,018,141
Balancing authority codeSWPP

Retirement

EIA-860M September 2026StatusAt least half of the plant's in-service nameplate capacity is scheduled to retire, on dates its owner has reported to EIA. As of EIA-860M for September 2026.
Next scheduled retirement
December 2036
Last scheduled retirement
December 2040
Capacity scheduled to retire
1,080 MW
Generators scheduled to retire
3
Share of in-service capacity scheduled
100%
Capacity still in service
1,080 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Natural Gas Steam Turbine360 MWScheduled to retireDecember 2036
2Natural Gas Steam Turbine360 MWScheduled to retireDecember 2038
3Natural Gas Steam Turbine360 MWScheduled to retireDecember 2040

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
230 kV
Transmission or distribution system owner
Southwestern Public Service Co
Balancing authority
Southwest Power Pool
NERC region
MRO
Transmission lines within 25 km (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Southwestern Public Service Co Operator EIA-860M
Xcel Energy Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • Stated Unit 3 scheduled to retire, 360 MW · EIA-860M
  • Stated Unit 2 scheduled to retire, 360 MW · EIA-860M
  • Stated Unit 1 scheduled to retire, 360 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · OpenStreetMap · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

© OpenStreetMap contributors

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Project Matador Gas Plant (PMG) Under construction Gas, combined cycle 16.3 km 11,679.3
Project Matador Nuclear Announced Nuclear 16.3 km 4,468
Majestic 2 Wind Farm Postponed Wind 18.0 km 79.2

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026