Jack Fusco Energy Center — Power plant · Gas, combined cycle · Brazos Valley EnergyJack Fusco Energy Center — Postponed · Gas, combined cycle · TX · 400 MW · 0.0 mi awayCrowned Heron 2 - Storage, LLC — Built · Storage · TX · 154.2 MW · 0.7 mi awayRock Rose Energy Storage — Under construction · Storage · TX · 208.5 MW · 8.6 mi awayImperial Power Plant LLC — Postponed · Gas, reciprocating engine · TX · 12 MW · 10.2 mi awayTX17 Nickel Prairie Storage — Postponed · Storage · TX · 100 MW · 14.3 mi away
  • Combustion
  • Storage
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Jack Fusco Energy Center

Power plant · Gas, combined cycle

Key facts

Power plant · Gas, combined cycleran 62% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2003
Net generation, 2025
3,645,651 MWh
Grid
345 kV to CenterPoint Energy (MISO)
Location
Fort Bend County, Texas

Output

Net generation MWh by year, 2003 to 2026
Fuel burned MMBtu by year, 2003 to 2026
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
Age
23 years since 2003
Unused energy
2,273 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
7,325 Btu/kWh 2025
All 8 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Parents
Name
Constellation Energy Corp
Share pct
100
Gem entity id
E100001000208
Unit ids
G100000401893
Location id
L100000401758
Eia plant ids
55357
Grid
Nerc region
TRE
Report year
2025
Grid voltage kv
345
Transmission owner
CenterPoint Energy
Balancing authority code
MISO
Balancing authority name
Midcontinent Independent Transmission System Operator, Inc..
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110022938419
Subparts reported
D
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1000798
Fuel burned (MMBtu), 202526,705,600
Capacity factor, 20250.616
Heat rate (Btu/kWh), 20257,325.3
Net generation (MWh), 20253,645,651
Balancing authority codeERCO

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Brazos Valley Energy Operator EIA-860M
CPN MANAGEMENT LP Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · GEM · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Jack Fusco Energy Center Postponed Gas, combined cycle 0.0 mi 400
Crowned Heron 2 - Storage, LLC Built Storage 0.7 mi 154.2
Rock Rose Energy Storage Under construction Storage 8.6 mi 208.5
Imperial Power Plant LLC Postponed Gas, reciprocating engine 10.2 mi 12
TX17 Nickel Prairie Storage Postponed Storage 14.3 mi 100

Sources EIA-860M · ERCOT

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • ERCOTOpen license · retrieved Nov 4, 2026

Attribution