Key facts

Power plant · Storage Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2023
Net generation, 2025
-297 MWh
Grid
12 kV to AEP Texas Central Company (ERCO)
Location
Kimble County, Texas

Output

Net generation MWh by year, 2024 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Storage source: “Batteries”
Age
3 years since 2023
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
TRE
Report year
2025
Grid voltage kv
12.50
Transmission owner
AEP Texas Central Company
Balancing authority code
ERCO
Balancing authority name
Electric Reliability Council of Texas, Inc.
Fuel burned (MMBtu), 20250
Net generation (MWh), 2025-297
Balancing authority codeERCO
Data notes (1)
  • Capacity factor, 2025 not shown: net generation -297.0 MWh is not positive (the plant consumed at least as much as it produced over the year)

Ownership

4 companies4
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
HEN Infrastructure, L.L.C. Operator EIA-860M
Manulife Infrastructure II Holdings A, L.P. Owner 52.9% 31 Dec 2025 EIA-860
Hunt Energy Network, LLC Owner 4.0% 31 Dec 2025 EIA-860
John Hancock Funding Company Owner 43.1% 31 Dec 2025 EIA-860

Timeline

  • In service · EIA-860M