Show on map
- Storage
- Operating
- 10 · 100 · 1,000 MW
Map
- Storage
- Operating
Junction (TX): location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Junction (TX)
Power plant · Storage
Key facts
Power plant · Storage Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2023
- Net generation, 2025
- -297 MWh
- Grid
- 12 kV to AEP Texas Central Company (ERCO)
- Location
- Kimble County, Texas
- Operated by
- HEN Infrastructure, L.L.C.
Output
Details
Who’s behind it
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Storage source: “Batteries”
- Age
- 3 years since 2023
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 0 |
| Net generation (MWh), 2025 | -297 |
| Balancing authority code | ERCO |
Data notes (1)
- Capacity factor, 2025 not shown: net generation -297.0 MWh is not positive (the plant consumed at least as much as it produced over the year)
Ownership
4 companies4| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| HEN Infrastructure, L.L.C. | Operator | EIA-860M | ||
| Manulife Infrastructure II Holdings A, L.P. | Owner | 52.9% | 31 Dec 2025 | EIA-860 |
| Hunt Energy Network, LLC | Owner | 4.0% | 31 Dec 2025 | EIA-860 |
| John Hancock Funding Company | Owner | 43.1% | 31 Dec 2025 | EIA-860 |
Timeline
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA Open Data bulk file — Electricity (ELEC.zip; monthly plant net generation and fuel consumption since 2001)Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules