Kinsley Landfill Solar: location and 6 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Kinsley Landfill Solar
Power plant · Solar
Key facts
Power plant · Solarran 16% of 2025 Retiring- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2015
- Net generation, 2025
- 11,928 MWh
- Grid
- 13 kV to Public Service Elec & Gas Co (PJM)
- Location
- Gloucester County, New Jersey
- Operated by
- Public Service Elec & Gas CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Solar source: “Solar Photovoltaic”
- Age
- 11 years since 2015
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Fuel burned (MMBtu), 2025 | 40,699 |
| Capacity factor, 2025 | 0.158 |
| Net generation (MWh), 2025 | 11,928 |
| Balancing authority code | PJM |
Solar array
Solar array
The array area counts panels and inverters only, not buildings, fences or the whole site.
- Array area (acres)
- 29.4
- AC capacity (MW)
- 8.6
- DC capacity (MW)
- 11.2
- Mounting
- Fixed tilt
- Site type
- Name includes "landfill" (not on EPA's landfill list)
- Began operating
- 2015
Retirement
EIA-860M September 2026StatusAt least half of the plant's in-service nameplate capacity is scheduled to retire, on dates its owner has reported to EIA. As of EIA-860M for September 2026.- Next scheduled retirement
- December 2035
- Capacity scheduled to retire
- 8.6 MW
- Generators scheduled to retire
- 1
- Share of in-service capacity scheduled
- 100%
- Capacity still in service
- 8.6 MW
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| KINS | Solar Photovoltaic | 8.6 MW | Scheduled to retire | December 2035 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 13 kV
- Transmission or distribution system owner
- Public Service Elec & Gas Co
- Balancing authority
- PJM Interconnection, LLC
- NERC region
- RFC
Transmission lines within 15 mi (10)
- New Freedom - Beaver Brook 230 kV
- Thorofare - Deptford 230 kV
- Thorofare - Deptford 230 kV
- Eagle Point - Deptford 230 kV
- Gloucester Switching Station - Beaver Brook 230 kV
- Gloucester Switching Station - Eagle Point 230 kV
- Mickleton - Thorofare 230 kV
- Mickleton - Thorofare 230 kV
- West Deptford Energy Station - Mickleton 230 kV
- Monroe - Mickleton 230 kV
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Unit KINS scheduled to retire, 8.6 MW · EIA-860M
- In service · EIA-860M
Sources
6 sourcesSources EIA-860M · GEM · LBNL · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- USPVDBMap services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Deptford Solar One Postponed | Solar | 1.4 mi | 3 |
| Pettinos Solar Postponed | Solar | 9.6 mi | 1.2 |
| EQUINIX Unknown | Large load | 11.9 mi | |
| CROSS CONNECT SOLUTIONS Built | Large load | 11.9 mi | |
| 365 DATA CENTERS Built | Large load | 12.1 mi | |
| H5 DATA CENTERS Built | Large load | 12.1 mi |
Sources EIA-860M · EPA ICIS-Air