Show on map
- Wind & solar
- Storage
- Loads
- Under construction
- Operating
- Size not stated
- 10 · 100 · 1,000 MW
Map
- Wind & solar
- Storage
- Loads
- Under construction
- Operating
- Size not stated
Livingston Solar Farm: location and 17 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Livingston Solar Farm
Power plant · Solar
Key facts
Power plant · Solar Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2009
- Net generation, 2025
- 0 MWh
- Grid
- 13 kV to Public Service Elec & Gas Co (PJM)
- Location
- Middlesex County, New Jersey
- Operated by
- Rutgers, The State University of NJSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
- Technology
- Solar source: “Solar Photovoltaic”
- Age
- 17 years since 2009
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 0 |
| Net generation (MWh), 2025 | 0 |
| Balancing authority code | PJM |
Data notes (1)
- Capacity factor, 2025 not shown: net generation 0.0 MWh is not positive (the plant consumed at least as much as it produced over the year)
Solar array
Solar array
The array area counts panels and inverters only, not buildings, fences or the whole site.
- Array area (acres)
- 7.3
- AC capacity (MW)
- 1.2
- DC capacity (MW)
- 1.4
- Mounting
- Fixed tilt
- Site type
- Greenfield
- Began operating
- 2009
Timeline
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · GEM · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- USPVDBMap services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| BARCLAYS CAPITAL DATA CENTER Built | Large load | 2.6 mi | |
| EVOQUE DATA CENTER SOLUTIONS - PNJ1 Built | Large load | 2.6 mi | |
| NJ 1 DATA CENTER Built | Large load | 3.7 mi | |
| Prologis - SLCNJ001 - Community Solar Under construction | Solar | 4.6 mi | 3.2 |
| Milltown Onsite BESS Under construction | Storage | 4.9 mi | 13.2 |
| FIDESSA Built | Large load | 5.8 mi | |
| BPL NJ - Belmont Under construction | Solar | 6.1 mi | 1.8 |
| MORGAN STANLEY DATA CENTER Built | Large load | 6.1 mi | |
| Middlesex Energy Center LLC Postponed | Gas, combined cycle | 6.6 mi | 570 |
| Gateway Energy Center, LLC Postponed | Gas, combined cycle | 7.2 mi | 440 |
| BLOOMBERG DATA CENTER Built | Large load | 11.2 mi | |
| BARCLAYS CAPITAL DATA CENTER Built | Large load | 11.2 mi | |
| Elevate Arthur Kill Under construction | Storage | 13.0 mi | 15.1 |
| Coreweave Under construction | Large load | 13.3 mi | |
| Swiftsure Postponed | Storage | 13.8 mi | 121 |
| PROPOSED DATA CENTER DEVELOPMENT Under construction | Large load | 14.2 mi | |
| BPL NJ - Union Distribution Center Under construction | Solar | 14.8 mi | 1.5 |
Sources EPA ICIS-Air · EIA-860M · EPA ICIS-NPDES · FAA OE/AAA