- Storage
- Under construction
- Retired
- 10 · 100 · 1,000 MW
Map
- Storage
- Under construction
- Retired
MESA 2: location and 1 exact-grade project within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Mesa 2
Power plant · Storage
As filed: MESA 2
Key facts
Power plant · Storage Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2017
- Net generation, 2020
- -63 MWh
- Grid
- 13 kV to PUD 1 of Snohomish County (BPAT)
- Location
- Snohomish County, Washington
- Operated by
- PUD No 1 of Snohomish County - (WA)SourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Storage source: “Batteries”
- Age
- 9 years since 2017
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | BPAT |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- December 2020
- Capacity retired
- 2.4 MW
- Generators retired
- 1
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| MESA2 | Batteries | 2.4 MW | Retired | December 2020 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 13 kV
- Transmission or distribution system owner
- PUD 1 of Snohomish County
- Balancing authority
- Bonneville Power Administration
- NERC region
- WECC
Transmission lines within 15 mi (1)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Unit MESA2 scheduled to retire, 2.4 MW · EIA-860M
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Arlington Battery Energy Storage System Under construction | Storage | 12.9 mi | 25 |
Sources EIA-860M