Show on map
North Weslaco 138 kV line — Transmission lineJerboa Storage — Postponed · Storage · TX · 200 MW · 6.2 mi awayGunnar Reliability Project — Built · Storage · TX · 154.8 MW · 10.5 mi awayAccalia Point Solar, LLC — Studied · Solar · TX · 190.5 MW · 13.2 mi awayNorth Edinburg BESS 1 — Under construction · Storage · TX · 10 MW · 13.8 mi awayMesquite Clean Energy Center (BESS) — Under construction · Storage · TX · 10.1 MW · 13.8 mi away
  • Wind & solar
  • Storage
  • In development
  • Under construction
  • Operating
  • Other infrastructure
  • 10 · 100 · 1,000 MW

North Weslaco 138 kV line

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
138 kV
States crossed
US-TX
Owner (as stated)
AEP Texas

Details

Who’s behind it

Owner
AEP Texas

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
1
Substations at the ends (as the source names them)
North Weslaco
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itaep texas
HIFLD line ID301673
Voltage class100-161 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Jerboa Storage Postponed Storage 6.2 mi 200
Gunnar Reliability Project Built Storage 10.5 mi 154.8
Accalia Point Solar, LLC Studied Solar 13.2 mi 190.5
North Edinburg BESS 1 Under construction Storage 13.8 mi 10
Mesquite Clean Energy Center (BESS) Under construction Storage 13.8 mi 10.1

Sources EIA-860M · ERCOT

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • ERCOTOpen license · retrieved Nov 4, 2026

Attribution