Northwind Energy: location and 17 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Northwind Energy
Power plant · Wind
Key facts
Power plant · Windran 7% of 2012 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1986
- Net generation, 2012
- 8,056 MWh
- Location
- Contra Costa County, California
- Operated by
- Northwind Energy IncSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Output
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Wind source: “Onshore Wind Turbine”
- Age
- 40 years since 1986
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- December 2012
- Capacity retired
- 13 MW
- Generators retired
- 1
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GEN1 | Onshore Wind Turbine | 13 MW | Retired | December 2012 |
Grid
Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.Transmission lines within 15 mi (10)
Connection points within 15 mi (4)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Timeline
- Stated Unit GEN1 scheduled to retire, 13 MW · EIA-860M
- In service · EIA-860M
Sources
6 sourcesSources EIA-860M · GEM · LBNL · CAISO · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- CAISOSource: California ISO
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Buena Vista Energy LLC Postponed | Storage | 4.3 mi | 100 |
| Tres Vaqueros Wind Farms LLC Withdrawn | Wind | 5.1 mi | 28.3 |
| Aramis I Solar Project × 2 units Under construction | Storage | 6.9 mi | 200 |
| Rooney Ranch Filed | Wind | 8.5 mi | 21 |
| Sand Hill C Contracted | Wind | 8.9 mi | 80.8 |
| Sand Hill B Filed | Wind | 9.5 mi | 17 |
| Sand Hill A Filed | Wind | 9.6 mi | 13.5 |
| Oakley Generating Station Withdrawn | Gas, combined cycle | 11.4 mi | 672.3 |
| TESLA Power Project Postponed | Gas, combined cycle | 12.1 mi | 1,322 |
| Mulqueeney Wind Energy Under construction | Wind | 12.7 mi | 80 |
| NorCal FPV 1 (Pond 2) Under construction | Solar | 12.8 mi | 1.8 |
| NorCal FPV 1 Under construction | Solar | 12.8 mi | 10 |
| Pittsburg RV Solar Under construction | Solar | 13.2 mi | 2.8 |
| Bishop Ranch - BR 3-GG Under construction | Solar + storage | 13.7 mi | 1.9 |
| Bishop Ranch - BR 3-FF Under construction | Solar + storage | 13.7 mi | 1.4 |
| Bishop Ranch - BR 3-HH Under construction | Solar + storage | 13.7 mi | 1.4 |